APM Project Management Qualification (PMQ) Practice Exam

Question: 1 / 400

What defines change control within project management?

The evaluation of team performance and efficiency

The method to capture and assess requests to modify project scope

Change control in project management is primarily concerned with managing changes to the project's scope, ensuring that any alterations are systematically evaluated, approved, or rejected. This process involves capturing requests to modify the project scope and assessing their implications on timelines, costs, and resources. Change control is vital to maintain the project's direction and to prevent scope creep, which can lead to misalignment with project objectives.

The methodical approach taken in change control helps project managers ensure that changes are beneficial and strategically aligned with the project's goals. It involves documenting change requests, analyzing their impact, and facilitating discussions amongst stakeholders before any decisions are made. This structured process provides a framework for managing the complexities that come when changes are proposed during the project lifecycle.

Get further explanation with Examzify DeepDiveBeta

The approval of all project-related financial expenses

The analysis of risk associated with project deliverables